Q
Are there alternative energy procurement options other than the Ontario Power Authority Feed-in Tariff program?
A
At this point, there are no other programs that support biogas development in the form of an energy contract.
Q
Can biogas be considered under the OPA Clean Energy Standard Offer Program (CESOP)?
A
No, biogas would be eligible under OPA's FIT Program only.
Q
Do in-series meter (or behind the meter) configurations qualify for FIT?
A
As per a directive from Measurements Canada, an in-series metering configuration is not an eligible option under OPA’s FIT. For more details and updates related to this decision, please see http://fit.powerauthority.on.ca/Page.asp?PageID=924&ContentID=10261
Q
What is the overall process for OPA's FIT?
A
FIT Process Milestones, Timelines, and Payments (.pdf).
Q
What is Hydro One's Distance Limitation Rule and what could it mean for my biogas project?
A
Hydro One has It depends on voltage. For feeders <15kV (which covers most biogas), the maximum distance is effectively 12km. Although the majority of existing projects are within 12km of a DS, it does cut out many rural areas.
Q
What is the overall process for OPA's FIT?
A
FIT Process Milestones, Timelines, and Payments (.pdf).
Q
What are Hydro One's current Connection Impact Assessment (CIA) fees?
A
Hydro One's CIA fee schedule can be found at the following link: http://www.hydroone.com/Generators/Documents/Feed-In%20Tariff/Connection%20Impact%20Assessment%20(CIA).pdf
Q
What is considered a Future Contract Related Product under the OPA FIT program?
A
OPA has provided clarity on FCRP as referenced in their guidelines document posted on their website and accessible here.